Project Title:
Refurbishment of External Wall Finishes at LAK
Scope of Work:
Provision of all labour, materials, plant, tools, implementation, design, hoarding, scaffolding and all temporary works and enabling measures as necessary for the execution, completion and maintenance during Defects Liability Period for all works relating to the refurbishment of external wall finishes at MTR Lai King Station (LAK)
Contract No:
R4685.A-17C
Contract Sum:
HK$ 10,700,000.00
Commencement Date:
2018-03-14
Completion Date:
2019-09-18
Location:
Hong Kong, China
District:
Status:
Completed
Client Name:
MTR Corporation Limited
Project Type:
Refurbishment Works